Verallia has begun construction of three photovoltaic plants at its factories in Zaragoza, Seville and Azuqueca de Henares. Once operational, they will join the facilities already running in Figueira da Foz, Burgos, Gran Canaria and Montblanc, completing a network of seven solar plants associated with its production sites in Spain and Portugal.
The company estimates that their combined capacity will exceed 58,000 MWh a year and cover around 16% of Verallia Iberia’s electricity needs. The comparison with the consumption of more than 16,000 Spanish households is a figure provided by the company, not an additional measure of the electricity its factories will use.
Renewable generation alongside factories
The installations bring solar generation closer to production sites and are part of Verallia’s strategy to improve energy management and reduce its dependence on external sources. Glass-container manufacturing requires substantial energy consumption, so electricity generated at the facilities themselves can help meet part of industrial demand.
The 16% figure is an estimate of the plants’ electricity needs, not their total energy consumption. The available data do not specify the output of each individual installation or how much of the electricity generated will be consumed directly at each factory.
Batteries, an option still under consideration
Verallia is also considering adding battery storage systems to increase self-consumption. The company has not announced a final decision or provided details on the timing, capacity or investment for these systems. They are therefore a possibility under consideration, not a confirmed part of the three new plants.
Sara Rodríguez, Verallia Iberia’s Head of CSR and Communications, said that integrating renewables and improving production efficiency are elements of the industrial energy transition. She said the potential deployment could strengthen the company’s competitiveness and reduce its energy dependence; these assessments reflect Verallia’s position.
The rollout adds to Zaragoza’s modernisation
The new solar plant in Zaragoza is part of a modernisation process that includes the hybrid furnace brought into operation in April. According to information published about the project, the furnace investment amounted to €63 million and combines renewable electricity with natural gas or biofuels. The photovoltaic installation and the furnace are separate initiatives within the factory’s energy transition.
With the three new plants, Verallia expects all its production sites in Iberia to have an associated solar installation. The projected generation could provide renewable electricity for its operations, although the announced figures alone do not make it possible to determine the financial savings, the total emissions reduction or the level of energy autonomy each factory will achieve.